Overcome Hardships to Meet Deadlines, Empower Performance with Technology

08 Oct,2026

As a technician of Shanxi Jinbaodao Foundation Engineering Co., Ltd., I fully participated in the dynamic compaction construction for the high-fill foundation of a key industrial park project in Guangxi. Faced with a tight schedule, complex geology and persistent rainy weather, the project team organized construction scientifically. With refined site management and digital intelligent equipment, we worked day and night to complete all works on schedule with zero safety incidents and fulfilled the contract commitments.

This large-scale high-fill foundation project features undulating terrain, uneven backfill layers and high risks of differential settlement, requiring zoned dynamic compaction with multiple energy levels. The construction window coincided with the local rainy season. Continuous heavy rains flooded the site and saturated soil, making it hard for compaction machines to move. Multiple temporary suspensions greatly reduced available working hours.

The project team prepared a special rainy-season construction plan in advance and formed a closed-loop management mechanism: pre-construction planning, on-rain handling and post-rain acceptance. A full-site drainage network was deployed with 24-hour on-duty personnel. During heavy rain, we kept ongoing preparatory work including equipment maintenance and tamping point verification. The site was divided into independent zones following the principle of “tamp after drying”. Before resuming work, technicians checked moisture content and bearing capacity to guarantee foundation quality.

Multiple dynamic compaction machines of different energy levels were deployed. We adopted daily review meetings to dynamically optimize machine layout and implemented two-shift continuous operation to resolve schedule delays promptly.

Digital intelligent monitoring served as the core support. All compaction machines were equipped with Beidou positioning and sensor systems, replacing manual layout and paper recording. The system automatically collects and uploads data such as tamping coordinates, drop height, blow counts and settlement to the cloud for full traceability. Managers remotely monitor machine status and progress, while the system verifies construction parameters and alerts non-compliant points to prevent missed tamping, boosting both speed and quality.

This project makes me realize foundation engineering relies on both hard work and scientific management empowered by digital technology. Going forward, I will summarize experience of rainy-season construction and digital dynamic compaction, maintain strict technical control and support the company’s high-quality project delivery.

Zhang Bin